City of
Oak Creek
Common
Council Report
Meeting
Date:
April 15, 2008
Item
No.:
Recommendation: That the Common Council consider a motion to concur
with the recommendation of the CIP Committee to realign W. Drexel Avenue south
of the existing center line (Project No. 06010) (2nd Aldermanic
District).
Background: When design started on W. Drexel Avenue from S. 13th Street to S. 27th Street,
it was assumed that the road alignment would be centered on the existing
roadway. This would result in acquiring
ROW on both sides of the existing roadway to accommodate the expanded
section. As the design progressed, it
became apparent that there were major obstacles to be overcome. A portion of the needed ROW would have to be
obtained from Milwaukee County in Falk
Park. These lands were obtained by Milwaukee County using LAWCON funding. The acquisition of a portion of these lands requires
State and Federal signoffs, and will take 18 to 24 months to complete with
uncertainty until the last signoff is obtained.
The WDNR has determined that the Butler’s
Garter Snake and its habitat must be protected north of Drexel Avenue. This will result in collecting snakes in the
impacted area for a spring/summer prior to the start of construction, which
will delay the project an additional year.
There will be an unknown mitigation cost for the taking of the snake
habitat. Roadway construction costs will
be increased by the need to provide access to residents along the project
route. The collective cost in time and
dollars has dictated that alternative approaches be explored.
By
realigning W. Drexel Avenue
to the south, the Butler’s Garter Snake habitat would
not be disturbed and no land would need to be purchased from Falk Park. This option also allows the construction of
half of the roadway while keeping the existing roadway open. With this option, there will be some
additional impacts including purchasing of one or two structures, reevaluation
of wetlands, and contract amendment for redesign. The time needed to complete the project would
be reduced from five years to three years.
Fiscal Impact: Additional
costs for the project will be brought back to the Common Council for approval.
|
Prepared by:
Matthew J.
Sullivan, P.E.
Design Engineer
|
Respectfully submitted:
Patrick
DeGrave
City
Administrator
|
|
Approved by:
Wayne St. John, P.E.
City Engineer
|
|
|
Fiscal review by:
Beverly A. Buretta, CMC
City Clerk
|
|