City of
Common
Council Report
Meeting
Date:
March 18, 2008
Item
No.:
Recommendation: That the Common Council consider a motion to
award the Street Department Facility Renovation and Addition reconstruction
contract to the lowest responsive, responsible bidder, VJS Construction
Services (Project No. 06027) (2nd Ald. District)
Background: The cost of the project was estimated between
$4 million and $10 million depending on the option awarded for the proposed
improvements. Angus-Young Associates
prepared the plans and specifications for the project and the work was
advertised. The following bids were
received.
Contractor Cost
|
Contractor |
Base Bid |
Alternative #1 (Base + Alt #1) |
Alternative #2 (Base + Alt #1 + Alt #2) |
|
VJS Construction |
$3,592,000 |
$2,070,000 ($5,662,000) |
$1,319,000 ($6,981,000) |
|
Miron Construction |
$3,768,000 |
$2,108,285 ($5,876,285) |
$1,470,807 ($7,347,092) |
|
Jansen Construction |
$4,000,000 |
$2,053,000 ($6,053,000) |
$1,559,000 ($7,612,000) |
|
Platt Construction |
$3,974,429 |
$2,442,444 ($6,416,873) |
$1,884,688 ($8,301,561) |
Additional Project Cost
|
Item Description |
Base Bid |
Alternative #1 |
Alternative #2 |
|
Construction
Contingency |
$200,000 |
$325,000 |
$450,000 |
|
Remaining
Architectural Fee’s & Expenses |
$150,000 |
- |
- |
|
Permits |
$20,000 |
- |
- |
|
Material Testing |
$8,000 |
- |
- |
|
Construction Survey |
$3,000 |
- |
- |
|
Asbestos Abatement |
$25,000 |
- |
- |
|
Relocation |
$100,000 |
- |
- |
|
Construction
Engineering |
$50,000 |
- |
- |
|
Owner Provided
Items |
$120,000 |
- |
- |
|
Bond Issuance &
Interest |
$1,360,000 |
- |
- |
|
TOTAL |
$2,041,000 |
$2,186,000 |
$2,291,000 |
Fiscal Impact: Currently approximately $1,360,000 is
available through CIP funds.
Funding Options: The remaining funds will need to be borrowed
with options to be presented by city staff at a later date for the alternative
chosen.
|
Prepared by: Matthew J.
Sullivan, P.E. Design Engineer |
Respectfully submitted: Patrick
DeGrave City Administrator |
|
Approved by: City Engineer |
|
|
Fiscal review by: Beverly A. Buretta, CMC City Clerk |
|