Recommendation:  That the Common Council consider a motion to award the Street Department Facility Renovation and Addition reconstruction contract to the lowest responsive, responsible bidder, VJS Construction Services (Project No. 06027) (2nd Ald. District)

 

Background:  The cost of the project was estimated between $4 million and $10 million depending on the option awarded for the proposed improvements.  Angus-Young Associates prepared the plans and specifications for the project and the work was advertised.  The following bids were received. 

 

Contractor Cost

 

Contractor

Base Bid

Alternative #1

(Base + Alt #1)

Alternative #2

(Base + Alt #1 + Alt #2)

VJS Construction

$3,592,000

$2,070,000

($5,662,000)

$1,319,000

($6,981,000)

Miron Construction

$3,768,000

$2,108,285

($5,876,285)

$1,470,807

($7,347,092)

Jansen Construction

$4,000,000

$2,053,000

($6,053,000)

$1,559,000

($7,612,000)

Platt Construction

$3,974,429

$2,442,444

($6,416,873)

$1,884,688

($8,301,561)

 

Additional Project Cost

 

Item Description

Base Bid

Alternative #1

Alternative #2

Construction Contingency

$200,000

$325,000

$450,000

Remaining Architectural Fee’s & Expenses

$150,000

-

-

Permits

$20,000

-

-

Material Testing

$8,000

-

-

Construction Survey

$3,000

-

-

Asbestos Abatement

$25,000

-

-

Relocation

$100,000

-

-

Construction Engineering

$50,000

-

-

Owner Provided Items

$120,000

-

-

Bond Issuance & Interest

$1,360,000

-

-

TOTAL

$2,041,000

$2,186,000

$2,291,000

 

Fiscal Impact:  Currently approximately $1,360,000 is available through CIP funds.

 

Funding Options:  The remaining funds will need to be borrowed with options to be presented by city staff at a later date for the alternative chosen. 

Prepared by:

 

 

 

Matthew J. Sullivan, P.E.

Design Engineer

Respectfully submitted:

 

 

 

Patrick DeGrave

City Administrator

Approved by:

 

 

 

Wayne St. John, P.E.

City Engineer

 

 

 

Fiscal review by:

 

 

 

Beverly A. Buretta, CMC