City of Oak Creek
Common Council Report
Meeting Date: , 2007
Item No.:
Recommendation: That the Common Council consider a motion to authorize the transfer of the remaining balance from the Southbranch Industrial Park road reconstruction project (Project No. 04003) to the W. Drexel Avenue project (Project No. 06010).
Background: The Southbranch Industrial Park road reconstruction project is constructed and all accounts have been paid. The remaining balance would be used to cover the non-TIF eligible portions of the W. Drexel Avenue reconstruction project.
Fiscal Impact: There is currently about $664,558.23 of funding remaining in the W. Drexel Avenue project for the remainder of design. The remaining balance of $1,002,443.43 from Southbranch Industrial Park would be used to cover non-TIF eligible portions, including construction cost, environmental protection and real estate.
|
Prepared by:
Matthew J. Sullivan, P.E. Design Engineer |
Respectfully submitted:
Patrick DeGrave City Administrator |
|
Approved by:
Wayne St. John, P.E. City Engineer |
|
|
Fiscal review by:
Beverly A. Buretta, CMC City Clerk
|
|