City of Oak Creek

Common Council Report

 

Meeting Date:  June 20, 2006

 

Item No.:        

 

Recommendation:  That the Council move to authorize payment of the contract payment for Project No. 03052, Jenna Prairie #1, as listed on the attached summary report.

 

Background:  Consultants working on capital improvement projects are paid periodically for work completed. The listed contract progress payment is for work completed through April 28, 2006.

 

Fiscal Impact:  The listed contract invoice payment amounts to $2,579.50, and is to be paid with Developer-provided funding.

 

Prepared by:

 

 

 

J. John Ozolins

Senior Engineering Technician

Respectfully submitted:

 

 

 

Patrick DeGrave

City Administrator

 

Approved by:

 

 

 

Wayne St. John, P.E.

City Engineer

 

 

Fiscal review by:

 

 

 

Beverly A. Buretta, CMC

City Clerk

 

 

 

 

 

 

 

 

 

 

 

T:\Shared\WPFILES\CCREPORT\2006\Invoice Payments Through 4-28-06.doc