Recommendation: That the Common Council approve Resolution No. 10639-062006, accepting the workmanship and authorizing final payment to Payne & Dolan, Inc., for Project Nos. 03011 - 03019. These projects involved the installation of street improvements, under the 2003 Asphalt Street Paving Program, in E. County Line Rd., S. 10th Ave., E. Barton Rd., S. Shepard Ave., S. Shepard Hills Dr., S. Veronica Dr., 11th Ave., 12th Ave., O’Brien Rd., Oak La., Stonefield Dr., Stonefield Ct., Montana Ave. and cul-de-sacs in various locations city wide (1st, 3rd, 4th and 5th Aldermanic Districts)
Background: This project was authorized by the Common Council as part of the Capital Improvement Program, and was awarded on May 20, 2003.
Fiscal Impact: Final payment of $4,712.08 is to be paid with CIP and/or Utility provided funding, as applicable.
|
Prepared by:
J. John Ozolins Senior Engineering Technician |
Respectfully submitted,
Patrick DeGrave City Administrator |
|
Approved by:
Wayne St. John, P.E. City Engineer |
|
|
Fiscal review by:
Beverly A. Buretta, CMC City Clerk |
|
T:\Shared\WPFILES\CCREPORT\2006\2003 Paving Program Final Payment.doc
RESOLUTION NO. 10639-062006
BY:________________________________________
PAYNE & DOLAN, INC.
AND AUTHORIZING FINAL PAYMENT
E. County Line Rd., S. 10th Ave., E. Barton Rd., S. Shepard Ave., S. Shepard Hills Dr., S. Veronica Dr., 11th Ave., 12th Ave., O’Brien Rd., Oak La., Stonefield Dr., Stonefield Ct., Montana Ave. & cul-ce-sacs in various locations
2003 ASPHALT STREET PAVING PROJECTS
PROJECT NOS. 03011 - 03019
(1st, 3rd, 4th & 5th ALDERMANIC DISTRICTS)
WHEREAS, the City of Oak Creek, hereinafter referred to as the City, and Payne & Dolan, Inc., hereinafter referred to as the contractor, entered into a contract whereby the Contractor agreed to perform certain public works under Project Nos. 03013 - 03019 for the installation of street improvements under the 2003 Asphalt Street Resurfacing/Reconstruction Program in the City of Oak Creek, in accordance with plans and specifications prepared by the City Engineer for the agreed price of $492,207.58; and,
WHEREAS, said total final contract price has been determined to be $519,299.86 as computed by the City Engineer using actual quantities, as measured, additions and deletions to the contract, and contract unit prices; and,
WHEREAS, the Contractor has completed all of the work set out in the specifications; and,
WHEREAS, the City Engineer has submitted his final report certifying that the workmanship of the Contractor is satisfactorily completed and recommends a final settlement be made and that the City accept the work and authorize the payment of the balance presently outstanding and due the Contractor, and that there remains a balance on account, the sum of $4,712.08.
NOW, THEREFORE, BE IT RESOLVED that the recommendation and report prepared by the City Engineer be accepted.
BE IT FURTHER RESOLVED that the City of Oak Creek does hereby accept the workmanship furnished by the Contractor, subject, however, to all guarantees and other obligations set out in the contract which the City of Oak Creek hereby reserves, if any, and subject to the right of the City of Oak Creek to commence an action or file a third party claim against the Contractor in the event that an action is commenced by anyone against the City of Oak Creek as a result of alleged injuries or wrongful death as a result of the condition of the work site or any other condition related to this project.
BE IT FURTHER RESOLVED that in order to guarantee said workmanship and materials on the street improvements for a period of 12 months after the acceptance of the work, the performance or contract bond, which has been made a part of the contract, shall be in effect until 12 months after the passage of the resolution.
BE IT FURTHER RESOLVED that the City, through its proper officials, issues its voucher in the sum of $4,712.08 to the Contractor in full and final payment of the City’s obligations under this contract.
Introduced at a regular meeting of the Common Council of the City of Oak Creek held this 20th day of June, 2006.
Passed and adopted this 20th day of June, 2006.
___________________________________
President, Common Council
Approved this 20th day of June, 2006.
___________________________________
Mayor, City of Oak Creek
ATTEST:
__________________________ VOTE: AYES ______ NOES ______
City Clerk
T:\Shared\WPFILES\CCREPORT\2006\2003 Paving Program Final Payment.doc