City of Oak Creek

Common Council Report

 

Meeting Date:  February 1, 2005

 

Item No.:         17

 

Recommendation:  That the Council move to authorize payment of the contract progress payment for Project No. 00019, as listed on the attached summary report.

 

Background:  Contractors working on capital improvement projects are paid periodically for work completed. The listed contract progress payment is for work completed through January 24, 2005.

 

Fiscal Impact:  The listed contract progress payments amount to $4,832.02, and are to be paid with CIP and or Utility provided funding, as applicable.

 

Prepared by:

 

 

 

J. John Ozolins

Senior Engineering Technician

Respectfully submitted,

 

 

 

Barbara S. Blumenfield, Ph.D

City Administrator

 

Approved by:

 

 

 

Wayne St. John, P.E.

City Engineer

 

 

Fiscal review by:

 

 

 

Beverly A. Buretta, CMC

City Clerk

 

 

 

 

 

 

 

 

 

 

 

 

 

T:\Shared\WPFILES\CCREPORT\Progress Payments Through 1-24-05.doc