City of Oak Creek

Common Council Report

 

Meeting DateJune 1, 2004

 

Item No.:         19

 

Recommendation:  That the Council move to authorize payment of the contract progress payments for Project No. 00049, Chapel Hills Park renovation, as listed on the attached summary report.

 

Background:  Contractors working on capital improvement projects are paid periodically for work completed. The listed contract progress payment is for work completed through May 25, 2004

 

Fiscal Impact:  The listed contract progress payment amounts to $5,118.00, and is to be paid with CIP and or Utility provided funding, as applicable.

 

Prepared by:

 

 

 

J. John Ozolins

Senior Engineering Technician

Respectfully submitted,

 

 

 

Wayne St. John, PE

City Engineer

 

 

Fiscal review by:

 

 

 

Beverly A. Buretta, CMC

City Clerk

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

T:\Shared\WPFILES\CCREPORT\00049 Progress Payment Through 5-25-04.doc