City of Oak Creek
Common Council Report
Meeting Date:
Item No.: 8
Recommendation: That the Council move to authorize payment of the contract progress payments for Project Nos. 96028, 00019, 04005, 04011 and 04017, as listed on the attached summary report.
Background: Contractors working on capital improvement projects are paid periodically for work completed. The listed contract progress payments are for work completed through October 8, 2004.
Fiscal Impact: The listed contract progress payments amount to $262,923.89, and are to be paid with CIP and or Utility provided funding, as applicable.
|
Prepared by:
J. John Ozolins Senior Engineering Technician |
Respectfully submitted,
Barbara S. Blumenfield, Ph.D City Administrator
|
|
Approved by:
Wayne St. John, P.E. City Engineer |
|
|
Fiscal review by:
Beverly A. Buretta, CMC City Clerk |
|
T:\Shared\WPFILES\CCREPORT\Progress Payments Through 10-8-04.doc