City of Oak Creek
Common Council Report
Meeting Date: September 2, 2003
Item No.: 19
Recommendation: That the Common Council move to authorize payment of the contract progress payments for Project No. 01006, as listed on the attached summary report.
Background: Contractors working on capital improvement projects are paid periodically for work completed. The listed contract progress payments are for work completed through July 31, 2003.
Fiscal Impact: The listed contract progress payment amounts to $ 322,300.07, and is to be paid with funding budgeted for the construction of the new police station.
|
Prepared by:
J. John Ozolins Senior Engineering Technician |
Respectfully submitted,
Robert L. Kufrin City Administrator |
|
Approved by:
Wayne St. John, P.E. Director of Public Works |
Fiscal review by:
Beverly A. Buretta, CMC City Clerk |
T:\Shared\WPFILES\CCREPORT\01006 Progress Payments Through 7-31-03.doc