City of Oak Creek
Common Council Report
Meeting Date: September 2, 2003
Item No.: 18
Recommendation: That the Common Council move to authorize payment of the contract progress payments for Project Nos. 03014, 00027, 03017 and 03015, as listed on the attached summary report.
Background: Contractors working on capital improvement projects are paid periodically for work completed. The listed contract progress payments are for work completed through August 25, 2003.
Fiscal Impact: The listed contract progress payment amounts to $374,154.47, and is to be paid with capital improvement and/or utility funding, as applicable.
|
Prepared by:
J. John Ozolins Senior Engineering Technician |
Respectfully submitted,
Robert L. Kufrin City Administrator |
|
Approved by:
Wayne St. John, P.E. Director of Public Works |
Fiscal Review by:
Beverly A. Buretta, CMC City Clerk |
T:\Shared\WPFILES\CCREPORT\Progress Payments Through 8-25-03.doc