City of Oak Creek
Common Council Report
Meeting Date: June 17, 2003
Item No.:
Recommendation: That the Common Council move to authorize payment of the contract progress payments for Project Nos. 99049, 01006 and 03005, as listed on the attached summary report.
Background: Contractors working on capital improvement projects are paid periodically for work completed. The listed contract progress payments are for work completed through June 9, 2003.
Fiscal Impact: The total listed contract progress payments amount to $328,333.76, and are to be paid with capital improvement and/or TIF funding, as applicable.
|
Prepared by:
J. John Ozolins Senior Engineering Technician |
Respectfully submitted,
Robert L. Kufrin City Administrator |
|
Approved by:
Wayne St. John, P.E. Director of Public Works |
Fiscal review by:
Beverly A. Buretta, CMC City Clerk |
File name: T:\Shared\WPFILES\CCREPORT\Progress Payments Through 6-9-03.doc