Recommendation: That the Common Council move to authorize a payment of $402.55 to Milwaukee County for their work on the 10th Street and Rawson Avenue traffic signal in conjunction with the 10th Street reconstruction project (Project No. 97037) (1st Aldermanic District).
Background: The project involves the relocation of some of the signal equipment due to the widening of the intersection radii. The project payment summary is below:
|
Original contract amount |
N/A* |
Amount completed to date |
$2,550.80 |
|
|
Changes to contract |
N/A |
Amount previously paid |
$2,148.25 |
|
|
Revised contract amount |
N/A |
AMOUNT THIS INVOICE |
||
|
* time and material work |
(Invoice No. 1001) |
This is the 2nd and final payment to Milwaukee County for this work.
Fiscal Impact: The above contract invoice payment amount is to be paid with capital improvement funds from Project No. 97037.
Prepared February 21, 2003 by:
Michael J. Sullivan, P.E.
Design Engineer
Approved February 21, 2003 by:
Wayne St. John, P.E.
Director of Public Works
Respectfully submitted,
Robert L. Kufrin
City Administrator
Fiscal Review by:
Beverly A. Buretta, CMC
City Clerk
T:\Shared\WPFILES\CCREPORT\97037 Milwaukee County Invoice 1001.doc