| 2005 ROAD IMPROVEMENT PROJECTS | ||||||||||||||
| Bid Date: April 29, 2005 | Payne & Dolan | Black Diamond | Stark Asphalt | |||||||||||
| Item | Unit | Total | Unit | Total | Unit | Total | ||||||||
| No. | Item Description | Quantity | Price | Price | Price | Price | Price | Price | ||||||
| 1 | Saw cut asphalt pavement | 3,345 | LF | $0.97 | $3,244.65 | $0.90 | $3,010.50 | $0.90 | $3,010.50 | |||||
| 2 | Saw cut concrete pavement | 1,415 | LF | $1.30 | $1,839.50 | $1.65 | $2,334.75 | $1.65 | $2,334.75 | |||||
| 3 | Remove asphalt pavement | 395 | SY | $3.45 | $1,362.75 | $2.85 | $1,125.75 | $2.70 | $1,066.50 | |||||
| 4 | Remove concrete pavement | 2,270 | LF | $3.08 | $6,991.60 | $3.00 | $6,810.00 | $3.15 | $7,150.50 | |||||
| 5 | Remove curb & gutter | 180 | LF | $3.40 | $612.00 | $5.00 | $900.00 | $3.50 | $630.00 | |||||
| 6 | Remove & replace curb & gutter | 260 | LF | $22.00 | $5,720.00 | $33.50 | $8,710.00 | $22.00 | $5,720.00 | |||||
| 7 | Match Curb & Gutter | 42 | EA | $30.00 | $1,260.00 | $24.00 | $1,008.00 | $30.00 | $1,260.00 | |||||
| 8 | Remove asphalt pavement, milling 2"-3" | 8,520 | SY | $0.68 | $5,793.60 | $1.06 | $9,031.20 | $1.10 | $9,372.00 | |||||
| 9 | Concrete curb & gutter | 170 | LF | $40.00 | $6,800.00 | $19.80 | $3,366.00 | $40.00 | $6,800.00 | |||||
| 10 | Concrete pavement, 5" | 19 | SY | $33.00 | $627.00 | $52.00 | $988.00 | $33.00 | $627.00 | |||||
| 11 | ADA curb ramp | 3 | EA | $425.00 | $1,275.00 | $440.00 | $1,320.00 | $425.00 | $1,275.00 | |||||
| 12 | Unclassified excavation | 1,115 | CY | $9.90 | $11,038.50 | $12.30 | $13,714.50 | $9.70 | $10,815.50 | |||||
| 13 | Undercut | 75 | TON | $19.50 | $1,462.50 | $15.00 | $1,125.00 | $14.00 | $1,050.00 | |||||
| 14 | Crushed aggregate base course | 1,230 | TON | $10.55 | $12,976.50 | $9.50 | $11,685.00 | $10.60 | $13,038.00 | |||||
| 15 | Pulverize, shape & compact asphalt | 52,535 | SY | $0.92 | $48,332.20 | $1.09 | $57,263.15 | $1.38 | $72,498.30 | |||||
| 16 | Asphalt pavement base repair | 1,005 | SY | $3.35 | $3,366.75 | $3.20 | $3,216.00 | $4.30 | $4,321.50 | |||||
| 17 | Asphalt binder | 8,565 | TON | $26.50 | $226,972.50 | $26.50 | $226,972.50 | $27.60 | $236,394.00 | |||||
| 18 | Asphalt surface | 4,400 | TON | $31.75 | $139,700.00 | $31.45 | $138,380.00 | $32.30 | $142,120.00 | |||||
| 19 | Manhole adjusting ring | 32 | EA | $100.00 | $3,200.00 | $127.00 | $4,064.00 | $125.00 | $4,000.00 | |||||
| 20 | Adjust sanitary manhole | 1 | EA | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | |||||
| 21 | Stone shoulder | 890 | TON | $22.70 | $20,203.00 | $26.00 | $23,140.00 | $22.10 | $19,669.00 | |||||
| 22 | Seed restoration | 840 | SY | $3.30 | $2,772.00 | $6.75 | $5,670.00 | $6.70 | $5,628.00 | |||||
| 23 | Pavement marking crosswalk epoxy 4" | 44,290 | LF | $0.34 | $15,058.60 | $0.35 | $15,501.50 | $0.34 | $15,058.60 | |||||
| 24 | Pavement marking crosswalk epoxy 6" | 470 | LF | $3.10 | $1,457.00 | $3.10 | $1,457.00 | $3.10 | $1,457.00 | |||||
| 25 | Pavement marking channelizing epoxy 8" | 47 | LF | $0.80 | $37.60 | $0.80 | $37.60 | $0.80 | $37.60 | |||||
| 26 | Pavement marking stop line epoxy 12" | 178 | LF | $3.40 | $605.20 | $3.40 | $605.20 | $3.40 | $605.20 | |||||
| 27 | Pavement marking diagonal epoxy 12" | 90 | LF | $3.40 | $306.00 | $3.40 | $306.00 | $3.40 | $306.00 | |||||
| 28 | Repair storm structure | 8 | EA | $750.00 | $6,000.00 | $755.00 | $6,040.00 | $750.00 | $6,000.00 | |||||
| 29 | Remove & replace catch basin | 1 | EA | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | |||||
| 30 | Traffic Control, Forest Hill Avenue | 1 | LS | $3,000.00 | $3,000.00 | $400.00 | $400.00 | $1,200.00 | $1,200.00 | |||||
| 31 | Replace Traffic Detector Loops, Forest Hill Avenue | 1 | LS | $1,742.00 | $1,742.00 | $1,750.00 | $1,750.00 | $1,900.00 | $1,900.00 | |||||
| TOTAL | $537,756.45 | $553,931.65 | $579,344.95 | |||||||||||