| Bid Tab - Oak Creek DPW - Additions and Renovations March 13, 2008 | |||||||||
| Contractor | Prequalification Statement | Bid Bond or Check | Subcontractor's Listing | Change Order Percentage | Unit Costs Form | Addenda #1 Acknowledged | Base Bid | Alternate #1 (Base Bid + Alt #1) | Alternate #2 (Base Bid + Alt #1 + Alt #2) |
| VJS | x | x | x | 10% | x | x | $3,592,000 | $2,070,000 ($5,662,000) | $1,319,000 ($6,981,000) |
| Miron | x | x | x | 15% | x | x | $3,768,000 | $2,108,285 ($5,876,285) | $1,470,807 ($7,347,092) |
| Jansen | x | x | x | 18% | x | x | $4,000,000 | $2,053,000 ($6,053,000) | $1,559,000 ($7,612,000) |
| Platt | x | x | 15% | x | x | $3,974,429 | $2,442,444 ($6,416,873) | $1,884,688 ($8,301,561) | |