| PROJECT NOS. 04008 SHEPARD AVENUE STORM SEWER | |||||||||||
| Bid Date: July 22, 2005 | Musson Bros. | Rawson Contractors | A.W. Oakes | C.W. Purpero | |||||||
| Item | Unit | Total | Unit | Total | Unit | Total | Unit | Total | |||
| No. | Item Description | Quantity | Price | Price | Price | Price | Price | Price | Price | Price | |
| 1A | 30" storm sewer, granular backfill | 245 | LF | $132.90 | $32,560.50 | $150.00 | $36,750.00 | $157.00 | $38,465.00 | $210.00 | $51,450.00 |
| 2A | 30" storm sewer, spoil backfill | 285 | LF | $96.00 | $27,360.00 | $100.00 | $28,500.00 | $110.00 | $31,350.00 | $160.00 | $45,600.00 |
| 3A | 24"H x 38" W HE-III RCP storm sewer, granular backfill | 53 | LF | $110.00 | $5,830.00 | $250.00 | $13,250.00 | $189.00 | $10,017.00 | $197.00 | $10,441.00 |
| 4A | 12" storm sewer, spoil backfill | 30 | LF | $56.70 | $1,701.00 | $95.00 | $2,850.00 | $100.00 | $3,000.00 | $73.00 | $2,190.00 |
| 5A | 12" RC flared end section | 1 | EA | $680.00 | $680.00 | $750.00 | $750.00 | $500.00 | $500.00 | $415.00 | $415.00 |
| 6A | 24" x 38" RC flared end section | 1 | EA | $1,175.00 | $1,175.00 | $1,500.00 | $1,500.00 | $1,000.00 | $1,000.00 | $995.00 | $995.00 |
| 7A | 60" storm manhole | 3 | EA | $2,725.00 | $8,175.00 | $3,000.00 | $9,000.00 | $3,550.00 | $10,650.00 | $3,150.00 | $9,450.00 |
| 8A | 72" storm manhole | 1 | EA | $3,175.00 | $3,175.00 | $3,500.00 | $3,500.00 | $3,700.00 | $3,700.00 | $3,035.00 | $3,035.00 |
| 9A | 16" diameter watermain offset | 1 | EA | $10,000.00 | $10,000.00 | $20,000.00 | $20,000.00 | $11,995.00 | $11,995.00 | $13,000.00 | $13,000.00 |
| 10A | 8" diameter watermain offset | 1 | EA | $7,250.00 | $7,250.00 | $8,000.00 | $8,000.00 | $8,675.00 | $8,675.00 | $11,000.00 | $11,000.00 |
| 11A | Sawcut asphalt pavement (full depth) | 333 | LF | $2.50 | $832.50 | $2.00 | $666.00 | $2.50 | $832.50 | $1.15 | $382.95 |
| 12A | Asphalt road restoration | 118 | SY | $35.00 | $4,130.00 | $35.00 | $4,130.00 | $34.50 | $4,071.00 | $39.00 | $4,602.00 |
| 13A | Driveway restoration | 525 | SF | $4.50 | $2,362.50 | $10.00 | $5,250.00 | $3.50 | $1,837.50 | $4.50 | $2,362.50 |
| 14A | Remove & dispose existing 15" RCP storm sewer | 163 | LF | $15.00 | $2,445.00 | $35.00 | $5,705.00 | $11.50 | $1,874.50 | $15.00 | $2,445.00 |
| 15A | Remove & dispose existing 12" CMP storm sewer | 27 | LF | $20.00 | $530.00 | $34.00 | $901.00 | $11.50 | $304.75 | $12.00 | $318.00 |
| 16A | Remove & dispose existing 60" storm manhole | 2 | EA | $750.00 | $1,500.00 | $450.00 | $900.00 | $750.00 | $1,500.00 | $260.00 | $520.00 |
| 17A | Relocate or adjust sanitary laterals | 3 | EA | $2,600.00 | $7,800.00 | $2,000.00 | $6,000.00 | $2,530.00 | $7,590.00 | $2,325.00 | $6,975.00 |
| 18A | Relocate or adjust water laterals | 3 | EA | $1,100.00 | $3,300.00 | $1,000.00 | $3,000.00 | $1,610.00 | $4,830.00 | $1,400.00 | $4,200.00 |
| 19A | Topsoil, seed, fertilize & mulch | 455 | SY | $6.50 | $2,957.50 | $10.00 | $4,550.00 | $7.00 | $3,185.00 | $7.00 | $3,185.00 |
| 20A | Topsoil, sod & fertilize | 74 | SY | $15.00 | $1,110.00 | $8.00 | $592.00 | $12.65 | $936.10 | $12.00 | $888.00 |
| 21A | Erosion mat | 10 | SY | $6.00 | $60.00 | $10.00 | $100.00 | $10.00 | $100.00 | $6.00 | $60.00 |
| 22A | Silt fence | 110 | LF | $5.00 | $550.00 | $3.00 | $330.00 | $5.00 | $550.00 | $4.00 | $440.00 |
| 23A | Traffic control | 1 | LS | $4,000.00 | $4,000.00 | $500.00 | $500.00 | $1,840.00 | $1,840.00 | $2,400.00 | $2,400.00 |
| TOTAL ITEMS 1A - 23A | $129,484.00 | $156,724.00 | $148,803.35 | $176,354.45 | |||||||
| PROEJCT NO. 05026 - ST. JOHN'S ESTATES STORM SEWER | |||||||||||
| Bid Date: July 22, 2005 | Musson Bros. | Rawson Contractors | A.W. Oakes | C.W. Purpero | |||||||
| Item | Unit | Total | Unit | Total | Unit | Total | Unit | Total | |||
| No. | Item Description | Quantity | Price | Price | Price | Price | Price | Price | Price | Price | |
| 1B | 24" storm sewer, spoil backfill | 792 | LF | $56.75 | $44,946.00 | $65.00 | $51,480.00 | $72.70 | $57,578.40 | $95.00 | $75,240.00 |
| 2B | 24" storm sewer, granular backfill | 176 | LF | $65.50 | $11,528.00 | $75.00 | $13,200.00 | $98.75 | $17,380.00 | $105.00 | $18,480.00 |
| 3B | 21" CMP, spoil backfill | 30 | LF | $46.50 | $1,395.00 | $50.00 | $1,500.00 | $80.00 | $2,400.00 | $95.00 | $2,850.00 |
| 4B | 42" precast storm manhole | 6 | EA | $1,560.00 | $9,360.00 | $1,500.00 | $9,000.00 | $2,070.00 | $12,420.00 | $1,600.00 | $9,600.00 |
| 5B | Sawcut asphalt pavement | 200 | LF | $2.50 | $500.00 | $2.00 | $400.00 | $2.50 | $500.00 | $1.15 | $230.00 |
| 6B | 8" diameter watermain offset | 1 | LS | $7,250.00 | $7,250.00 | $5,000.00 | $5,000.00 | $8,675.00 | $8,675.00 | $11,000.00 | $11,000.00 |
| 7B | Asphalt road restoration | 50 | SY | $35.00 | $1,750.00 | $25.00 | $1,250.00 | $34.50 | $1,725.00 | $39.00 | $1,950.00 |
| 8B | Driveway restoration | 200 | SF | $4.00 | $800.00 | $5.00 | $1,000.00 | $5.50 | $1,100.00 | $4.50 | $900.00 |
| 9B | Topsoil, seed, fertilize & mulch | 1,500 | SY | $5.50 | $8,250.00 | $10.00 | $15,000.00 | $7.00 | $10,500.00 | $5.25 | $7,875.00 |
| 10B | Erosion mat | 170 | SY | $6.00 | $1,020.00 | $10.00 | $1,700.00 | $10.00 | $1,700.00 | $4.50 | $765.00 |
| 11B | Shaping & grading | 100 | SY | $25.00 | $2,500.00 | $35.00 | $3,500.00 | $15.00 | $1,500.00 | $11.00 | $1,100.00 |
| 12B | Traffic control | 1 | LS | $4,000.00 | $4,000.00 | $500.00 | $500.00 | $1,000.00 | $1,000.00 | $1,800.00 | $1,800.00 |
| TOTAL ITEMS 1B - 12B | $93,299.00 | $103,530.00 | $116,478.40 | $131,790.00 | |||||||
| TOTAL BOTH PROJECTS | $222,783.00 | $260,254.00 | $265,281.75 | $308,144.45 | |||||||